BRF+ Transports fails with errors then BRF+ application inactive in target system.
Issue Explanation: When we import BRF+ application using transport from Dev system to SIT/UAT/Prod if transports imported with return code 12/8 then in target system that BRF+ application will be in active.
Then we have two options to fix issue
1. Using FDT_HELPERS tcode we can re import failed transports then it will activated BRF+ application in SIT/UAT/prod
Or
2. Create new transport with BRF+ application and import to target system if new transport import successful into target system then it will activate BRF+ application in Target system.
Here I am covering first option next blog I will cover second option
Step 1:
Please prepare transport before release
Step 2:
Then Release Transport in Source system
Step 3:
Please inform Basis to run import job to target system
Step 4:
Check transport import log
Tcode: SE01
Provide your transport and click on Log Tab
Step 5:
Transport fails with return error code 8
Step 6:
Open BRFPLUS workbench and check BRF+ application it will be inactive mode in target system
Step 6:
Login into target system and Open FDT_HELPERS tcode in target system
Step 7:
Expand BRFplus - Transport
Step 8:
Select BRFplus: Transport phase Execution
Step 9:
Click on Execute
Step 10:
Next you will see below screen
Step 11:
Provide your transport like below and select radio button After import Processing then click on Execute button
Step 12:
It will show you result is successfully generated BRF+ application in target system