Last month, I had the pleasure in colaborate with a brazilian food company (the world's tenth-largest food company) speaking about some of our experiences, best practices and provide on demand consulting for their ChaRM Change Request Management Solution.
During our conversation the customer tell to me your wish to deploy Transport of Copies as part of the Urgent Changes flow. As we know, the Change Request Management cover a standard workflow containing the transport of copies procedure available only on Normal Changes.
In this blog I provide some hints in how you could set it up, however there is no guarantee and also standard support from SAP for this configuration.
Background
Urgent Changes have their own tasklist (Type "H") to coordinate all transport requests. The original tasklist type H does not contain the action "Create Transport of Copies". In this case we need to enhace the tasklist type H using a custom tasklist variant. After this configuration, some ajustments must to be applied to control the TMS of managed system.
Just to clarify when the ToC will be generated and when the original Transport Request is released, I made the following pictures showing the "AS-IS" and "TO-BE" solution. You can adapt for your needs (e.g. creating additional status).
Standard Process Flow: Urgent Change (SMHF)
Enhanced Process Flow: Urgent Change (Y/ZMHF)
Configuration Procedure
Create a Tasklist Variant
Define Tasks for Tasklist Variant
Select all entries from Tasklist Variant "SAP0" and copy to Tasklist Variant "Y/ZSAP0":
Create a new record adding the task "Create Transport of Copies" for the Project Type "H Urgent Change":
Define Header / Footer Tasks for Tasklist Variant
Register Tasklist Variant into Project Cycle
Adjusting Conditions and Actions (TSCOM Tables)
Some activities regarding the transport management system and consistency checks are triggered when the change document is assigned to a specific status value. To enable the urgent change flow to generate transport of copies, we need to change some actions and their conditions based on status value.
Result
Project cycles powered by the custom tasklist variant will be able to generate Transport of Copies. In my next blog I will describe how to use this feature.