This document describes about planning material and how it can be used for capacity analysis .
The Standard SAP capacity planning does not assist a capacity availability check at the sales order; but we can check it with help of pre-planning material.
About Planning Materials?
Some of the highlight of planning material.
Example:
Let consider the below scenario:
Finished products FGP01 and FGP02 are being produced in the same production line .Here assumption is production line or Work centers are considered as ‘Planning material ‘ and the plant capacity are entered as Planned Independent requirement of ‘Planning material’.
Master Data Settings:
Planning Material:
Strategy : 60
FG Material:
Strategy : 65
Planning Material,Planning Plant and conversion factor (MRP3).
It always suggested that use same UOM between Planning material(PM) and FG. If we know correct conversion factor between the UOM of PM and FG we need to maintain it in Material master to get the accurate availability .
Step 1: Create available Plant/ Work center capacity : ( i.e Create the Planned Independent requirement for Planning material.)
D 13.10.2014 120
D 14.10.2014 120
D 15.10.2014 120
D 16.10.2014 100 (reduced capacity)
D 17.10.2014 120
D 20.10.2014 120
D 21.10.2014 120
D 22.10.2014 120
Make sure that PIR has the below requirement type and consumption Indicator
When MRP run is take place Non-convertible Planned order will be created for Planning materials.This will be used as basis for planning dependent parts of FG.
Step 2: Sale Order processing of Finished Goods:
Create Sale order for FGP02 (one of the FG assigned with Planning material)
Qty : 150 PCs
Date : 10/10/2014
System confirm this quantity only in two schedule as below. Reason is there is no capacity on 10/10/2014 (no PIR quantity is maintained for Planning material)
Let say I am changing the date into 17.10.2014 and performing availability check in SO.
Since PIR quantity (Capacity) on 13 and 14 th cover this requirement system confirm this quantity in 14-10-2014 itself.
Step 3: Capacity Reduction: ( Reduction of Planned Independent requirements)
Once sale order is created PIR of Planning material will be reduced (i.e capacity is assigned to sale order)
Here due to backward scheduling system consumed 120 qty from 14-10-2014 and 30 qty from 13-10-2014
Now if we create sale order for the other Finished goods FGP001 which is also using same work center or production line for the quantity 100 PC on 13-10-2014 system will only confirm 90 pcs (remaining PIR) and the 10 pcs will be confirmed on 15-10-2014 only.
Capacity utilization /load Analysis:
We can use transaction code MD73 to analyse the capacity situation at any time.
Here 13-10-2014 capacity of 120 PCs is fully utilized in which 100 pcs for FGP01 and 20 PCs for FGP02
On 14-10-2014 Capacity was completely utilized by Sale order of FGP02
When MRP is carried out for FGP01 and FGP02 system creates Planned order with type KD .
Advantages :
Available capacity in PCs or any UOM will be shown as PIR of Planning material
Capacity Utilization can be seen at any time.
Sale Orders delivery date will be calculated based on work centre capacity.
Work centers in which more than one similar products are produced ,capacity will be determined in Sale order stage itself.
Limitation:
We can not use this process for Stock transfer from other plant due to certain limitation in SAP.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
3 | |
2 | |
2 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 |