9 Replies Latest reply: Mar 5, 2012 9:00 AM by jigar patel RSS

Plant releted

Ravindra Chavan
Currently Being Moderated

Dear All

I have created plant through IMG - Enterprise structure , in Assignement by mistake plant got deleted ,can any body tell me how to

retrive that plant & assign it to company code.

  • Production order releted
    Ravindra Chavan
    Currently Being Moderated

    Dear All

    I am working on make to stock strategy i did MD61 - MD02 - but in MD04 when i go to convert pld order in to prod. order it is not

    going in as per regular root ,it is telling Enter order type. can any body help to resolve this

    • Re: Production order releted
      D R
      Currently Being Moderated

      Dear Sap User,

       

      In this you forgot to enter order type dependent parameter fill it and check it again.

       

      Rgrds,

      Dheeraj Rawal

    • Re: Production order releted
      Mangalraj Senthamaraikannan
      Currently Being Moderated

      Dear Chavan,

       

      1.You can mention the default order type either through assigning the production scheduling profile in the material master in the

       

      work scheduling view and in return the default order type can be included in OPKP for the particular prod.scheduling profile.

       

      2.Or else in OPPQ/OPPR you have to define the default order type that gets picked during planned order into production order.

       

      Regards

      Mangalraj.S

    • Re: Production order releted
      jigar patel
      Currently Being Moderated

      Hi,

      In OPPQ enter the plant-> maintain--> unter Maintain planned order select conversion and enter your order type.

       

       

      It will not ask order type on conversion.

       

      similarly you can maintain in OPPR also if you maintained material groups.

    • Re: Production order releted
      Jeevan Sagar
      Currently Being Moderated

      Please ask only one question per thread. It is in the forum rules.

       

      Coming to your question:

      Rchavan wrote:

       

      Dear All

      > I am working on make to stock strategy i did MD61 - MD02 - but in MD04 when i go to convert pld order in to prod. order it is not

      > going in as per regular root ,it is telling Enter order type. can any body help to resolve this

       

       

      The standard options you have are production scheduling profile, MRP group and Plant parameters,

       

      In OPKP: Here you can set different order type for different production scenarios like MTS, MTO etc. If production order is being created for stock, you can set it in the relevant field, if planned order was created from sales order you can set a different order type and if you want to create production order without material you can set a different type all these will to be automatically picked up if the leave the order type blank while creating production order manually or converting planned order to production order.

       

      In OPPR you can maintain one order type but this has priority only if you don't maintain anything OPKP.

       

      In OPPQ you can maintain one but this has the lowest priority.