I need to have an idea how to kick start the Process chains, i do have the process chains name. All I know the steps.

 

Thanks

  • Re: Process chain
    Ravi Shankar
    Currently Being Moderated

    Hi Vimal,

    Here are the steps to kick start the Process chains in BI 7.0

    1) Execute transaction RSPC

    2) Press 'Create', enter 'Name' and 'Description' of the process chain, press 'Continue'

    3) First step in the process chain will be a 'Start' step, press 'Create' to create a process variants

    4) Enter 'Name' and 'Description' of the process variant

    5) 'Save' process variant and go back, 'Change selections' is used to schedule the process chain, we will revisit this again later.

    6) Press 'Continue'

    7) Select the InfoPackage which is used to load data in Infocube, drag InfoPackage to right panel

    8) Select the process variants as InfoPackage using fucntion key F4

    9) Select the InfoPackage XXXX and press 'Continue'

    10) Following steps will be added in the process chain

    11) Join 'Start' step with step 'Indexes' by selecting 'Start' step and dragging the line to 'Indexes'

    12) Go back to 'Start' step and right click to 'Maintain Variant'

    13) Select 'Immediate' to schedule the process chain immediately

    14) 'Check' the process chain and 'Activate' the process chain

    15) Execute the process chain.

    16) Process chain will start executing, to check the status, Press

    17) Select 'Yesterday and Today' to check the status of the process chain

    19) Once completed, the status will appear, in-case there is any failure, the status will appear as canceled.

  • Re: Process chain
    Saranya Sadagopan
    Currently Being Moderated

    Hi Vimal,

     

    You can also view the status of the executed process chain by executing the program RSPC_MONITOR in SE38

     

     

    Regards,

    Saranya

  • Re: Process chain
    shilpa gudumasu
    Currently Being Moderated

    Hi Vimal,

    1.Please go to transaction code RSPC1

    2.Give chain name and press execute. Your required PC will be displayed.

    3.Check the start condition for your PC. Right click the start variant, press "Display/maintain variant.

    Go to "change selections"

    4. If it is immediate start, you come back to the PC and press execute symbol.Your PC will start immediately.

    Hope it is helpul.

    Regards,

    Shilpa

  • Re: Process chain
    Sai Prasad
    Currently Being Moderated

    Hi Vimal,

     

    Follow the steps suggested by Shilpa, monitor the PC in Log view and make sure it completes successfully.The above suggested steps helps in running the PC manually. But you may even schedule the PC to trigger automatically at regular intervals (hourly, daily, weekly or even monthly) by changing the Scheduling options to time/after event in 'Change Selections'.

     

    Let me know if its not clear.
    Regards
    Sai

    • Re: Process chain
      Rajesh Kumar Sinha
      Currently Being Moderated

      Hi Vimal,

       

      Go to SE37 and give the program : RSPC_API_CHAIN_START and click on execute.


      Now give the process chain name and execute, It will ask for Priority you can use Standard priority

       

      You can also check the Scheduling options by clicking on Start variant.

       

      You can change the scheduling option also.

       

      The above method will work in both the case...if it direct scheduling or through meta chain.

       

      Thanks,

       

      Rajesh

  • Re: Process chain
    Rajesh Kumar Sinha
    Currently Being Moderated

    Hi Vimal,

     

    Go to SE37 and give the program : RSPC_API_CHAIN_START and click on execute.


    Now give the process chain name and execute, It will ask for Priority you can use Standard priority

     

    You can also check the Scheduling options by clicking on Start variant.

     

    You can change the scheduling option also.

     

    The above method will work in both the case...if it direct scheduling or through meta chain.

     

    Thanks,

     

    Rajesh

  • Re: Process chain
    Harish Babu
    Currently Being Moderated

    Hi Vimal,

     

    Since you know the Process Chain name goto tcode rspc1 and give the Process Chain name in "Process Chain (ID)" filed, leave the log ID filed blank, uncheck 'display only' button and execute.

    --> then the process chain is displayed in planning view.

    -->since you said that the start condition of the PC is immediate, press the "Schedule(F8)" button present on tool bar or just press F8.

         This will run your process chain and you can verify from log view. If the Process Chain didnt start, then please verify the start condition of the Process Chain.

     

    Regards,

    Harish.