planning horizon MRP

Praneeth Nalla
Currently Being Moderated

Hi Gurus,

 

 

Planning horizon:

In OPPQ we define number of days.

Eg: Plant 2xxx. Planning horizon = 100 days.

 

Now, I'm expecting that if I have Planned indep requirements/sales orders beyond 100 days, MRP Run will not generate any planned orders/purchase requisitions.

 

TCode: MD61. created PIRs - 100 qty 03/05/2014, 03/05/2015

TCode: MD02 - Ran MRP.

TCode: MD04 - can see planned orders created on 03/05/2014 and 03/05/2015.

 

HELP!