Dear Experts
I created assessmet cycle "KEU1). There were 20 segmenets in this cycle.My sender is one cost center and recivers are:
Product From A - ZZZZZZ
Customer From A - ZZZZ
Material Group A - ZZZZ
Distrbtion Channel A - ZZZ
District A- ZZZZ
When I execute KEU5 in backgroud it took very long time and stopped.
My target is to distribute from cost center to all charcters and I do not want to use top down distribution.
Can you help
Ahmed Zain
Hi,
You might find this note 1389644 helpful.
Regards,
Eli
Dear Eli,
I tried the note but it is lower than my system grade Iam at 605 and this note is up to 604. Let me explain the problem in a clearer view:
I used cycles as follows:
1- I make apportionment cycles (KSU1, KSU2, KSU3, KSU5) to distribute the cost from central cost centers to my sales office cost center. There is no problem in these cycles.
2- Secondly, I need to send the cost from my sales office cost center to other charactes "tracing factor is variable portions with 5 (Revenue)".
| Receiver | From | TO | Group |
| Product | 10010 | 10999 | |
| Customer | 100000 | 999999 | |
| Company code | 1000 | ||
| District | 50000 | ||
| Division | 10 | 99 | |
| Dist Channel | 10 | 99 |
When I execute KEU5, it does not work.
Is this structure correct? how to distribute this cost?
Dear Ahmed,
DId you create summarization Levels. If not, try creating summarization levels. This might help the system to speed up the process of execution.
One Doubt... Are you using "Sender Cost Element Group" in the PA Assessment Cycle.
Best Regards
Surya