hi,
we have some 17 work centers existing. We asked to look into capacity planning, levelling and loading in work centers.
a total of 35 staff is allocated to mnt dept and orders are taken by their own on dial basis. some may sit ideal.
we want assign orders or operations to all the staff
how capacity planning is implemented in sap pm.
Please explain me steps with corresponding t codes.
thanks in advance.
RSV
sir,
someone please respond to my query.
RSV
Hi
Don't no how much it will help,
For Capacity Planning
you have to check Capacity Availability Setting in "Define Inspection Control" (OIOI)
Like No Check - should not be ticked.
Overall profile - SAPPM_G013 PM: Capacity availability check >= 3.0D
Collect. conversion - Here Select as per your requirement. (for eg.-3 No release if capacity is insufficient)
Then go to your work center there in Capacity Tab at the bottom there is another Capacity Tab Icon, click on it
here maintain as per following given as example
Capacity planner grp- MNT
Factory calendar ID- as you defined
Base unit of meas.- H
Start - 09:00:00
Finish -17:00:00
Length of breaks- 01:00:00
Capacity utilization - 100%
No. of indiv. cap.(for eg. No of People in this Work Center) - 1
Capacity 7.00 H
then save.
Here as per above example I have 1 WC which have 1 individual having cappacity of 7H.
One Maintenance order is created of 7 H, & released it.
Now again one maintenance order is created on same date & time having same timings
so when ever you go for releasing the maintenance order then as per your config setting in OIOI,
it will give you message that for Order No.XXXXX WC with Over Load.
Also refer below link may be helpful to you.
http://scn.sap.com/thread/3156892
Regards
Ritesh