it is posible without workcenter and task list can i make a plan and schedule the plan
actually client want to truck cost of maintenance he wants only start date of maintenance, end date of maintenance and the cost for the maintenance , he don't want the material used and service
he wants only on this date maintenance done and the amount on this same date spend for the maintenance
kindly tell me how can i map this scenario
hi
i think it is not possible to create maintenane plan without work center. also i think you can avoid the task list
how are you going to map the cost , you said they don't want material and service done
Regards
thyagarajan
You shall Create a Dummy Work Center and Dummy Task list but i am not sure how you can capture the cost with out the following
- Cost of Manpower
- Cost of Component
Please explain why you need in such a way?
You can create a single-cycle plan without a task list.
But you must enter a main work centre in the maintenance item.