I have one requirement regarding PR creation through CJ20N. In PS scenario, under one project there will be number of WBS elements and under each WBS element number of network will be there and under each Network there will be number of activities. We will add materials under these activities. There are two type of PR creations by releasing networks in CJ20N, they are
1) Network wise PR creation - through the network PR number will be same and line items will be different.
Example : P->W->N->A1-> M1 ---> PR1/1
M2 ---> PR1/2
A2-> M3 ---> PR1/3
M4 ---> PR1/4
2) Material wise PR creation - for every material, PR number will be different.
Example : P->W->N->A1-> M1 ---> PR1/1
M2 ---> PR2/1
A2 -> M3 ---> PR3/1
M4 ---> PR4/1
Through customization, we can create Network-wise PRs or Material-wise PRs. But my requirement is to create Activity-wise PRs, in which PR number will be same with in an activity and it will differ with another activity under same network.
Example : P->W->N->A1-> M1 ---> PR1/1
M2 ---> PR1/2
A2-> M3 ---> PR2/1
M4 ---> PR2/2
For this, there is no option in customization. Please let me know is this possible through enhancements/BADIs? or is there any other way to do?
Thanks in Advance,
Siva Sankar.
Dear Siva Sankar,
i am facing same problem as described by you. If you have got solution for this can you please share with me so that i can also solve this issue.
thanks
Sunil
Hi,
let me know what is the solution you assuming :-