4 Replies Latest reply: May 6, 2014 1:06 PM by Dhaneshwari Pareek RSS

Network wise PR creation in CJ20N (PS)

Siva Sankar Reddy Lankayapalli
Currently Being Moderated

Hi all,

 

I have one requirement regarding PR creation through CJ20N. In PS scenario, under one project there will be number of WBS elements and under each WBS element number of network will be there and under each Network there will be number of activities. We will add materials under these activities. There are two type of PR creations by releasing networks in CJ20N, they are

 

1) Network wise PR creation - through the network PR number will be same and line items will be different.

Example : P->W->N->A1-> M1   ---> PR1/1

                                        M2  ---> PR1/2

                                A2-> M3  ---> PR1/3

                                        M4  ---> PR1/4

 

2) Material wise PR creation - for every material, PR number will be different.

Example : P->W->N->A1-> M1  ---> PR1/1

                                         M2  ---> PR2/1

                                A2 -> M3  ---> PR3/1

                                         M4  ---> PR4/1

 

Through customization, we can create Network-wise PRs or Material-wise PRs. But my requirement is to create Activity-wise PRs, in which PR number will be same with in an activity and it will differ with another activity under same network.

Example : P->W->N->A1-> M1   ---> PR1/1

                                        M2  ---> PR1/2

                                A2-> M3  ---> PR2/1

                                        M4  ---> PR2/2

 

For this, there is no option in customization. Please let me know is this possible through enhancements/BADIs? or is there any other way to do?

 

Thanks in Advance,

Siva Sankar.