Change Request Management scenario: Working examples Final Points and Appendix
This blog is the last part of the working case initiated in SDN blog : Change Request Management scenario: Working examples.
Here you will find also the possible actions and statuses of normal and urgent corrections, change documents and test messages.
Final points to remember
Never leave the SDMN document in edit mode you can get action errors in the associated corrections like "No link to maintenance cycle". Put the SDMN document in display mode and recheck the correction to fix the error.
You can move the MC phase to previous phases and move up again.
In TEST phase don't work at all with your SDMJ corrections, only with SDHF corrections and with SDTM test messages.
In EMERGENCY CORRECTION phase don't work at all with your SDMJ and SDHF corrections because you only are allow to create a TR and released it by using the task list directly.
Usually customers are most of the time in Development with Release phase.
Every time you move the phase up check the warning to see the corrections that are not in the correct status for this phase and contact the responsible to see how to work with these corrections.
When you schedule task "Import Transport Request (Background)" check that if you are running this job from an urgent correction the command is: tp IMPORT SMMK900688 SMM clires200 U0, and this TR remains in the import buffer until you don´t execute the job "Import Transport Request (Background)" from the M* task list. This job will run a tp IMPORT ALL SMM clires200 proj=0001,SMM_P00044
Last point, manual deletion of CRM documents in Charm may lead to serious problems such as database inconsistencies, please see note 902973 "Unrestricted deletion of change transactions"
Note that I am always working with same user and not with the correct users, change manager, developer, tester, IT user, etc. In the appendix you will see the person in charge of each action in each MC phase.
Appendix A. Interesting transactions to know
- solar_project_admin: to manage the project
- crmd_order or crm_dno_monitor: to find your documents
- /tmwflow/maintinst: to see your SDHF document and see to which project are assigned and to see the project task list directly
- /tmwflow/proj: to see the CTS status Switches and in Project Structure tab the TRs assigned to each correction, see below.
- /tmwflow/cmsconf: System Change Options
- /tmwflow/trmo: Tracking
Appendix B. Change request SDCR possible actions per status
Step | Who- Where | User Status | Action | Final User Status | Details |
1 | Change Manager - Solman | To be Approved | Authorize Change Request | Authorized | |
1 | Change Manager - Solman | To be Approved | Reject ECR | | |
Appendix C. Normal correction possible actions per status
Step | Who- Where | Initial User Status | Action | Final User Status |
1 | Change Manager- Solman | Created | | |
2 | Developer- Solman | Created | Set to "In Development" | In Development |
Cancel Procedure | Withdrawn |
3 | Developer - Solman | In Development | Logon to System | In Development |
Complete Development | To be Tested |
Cancel Procedure | Withdrawn |
Create Transport Request | In Development |
Create Task | In Development |
Critical Transport Objects | In Development |
Test Transports | In Development |
Transport into Sandbox System | In Development |
Go to the Task Plan | In Development |
4 | Tester- Solman | To be Tested | Logon to System | To be Tested |
Confirm Successful Test | Consolidated |
Reset Status to "in Development" | In Development |
Go to the Task Plan | To be Tested |
5 | Change Manager- Solman | Consolidated | Logon to System | Consolidated |
Set Production Status | Production |
Start Retrofit | Consolidated |
Go to the Task Plan | Consolidated |
Appendix D. Urgent correction possible actions per status
Step | Who- Where | Initial User Status | Action | Final User Status |
1 | Change Manager- Solman | Created | | |
2 | Developer- Solman | Created | Set to "In Development" | In Development |
Withdraw Correction | Withdrawn |
3 | Developer - Solman | In Development | Logon to System | In Development |
Release Transport Request | |
Pass Correction to Test | To be Tested |
Withdraw Correction | Withdrawn |
Create New Transport Request | In Development |
Create Task | In Development |
Critical Transport Objects | |
Transport into Sandbox System | |
Go to the Task Plan | In Development |
4 | Tester- Solman | To be Tested | Logon to System | To be Tested |
Confirm Successful Test | Successfully Tested |
Reset Status to "In Development" | In Development |
Go to Task Plan | To be Tested |
5 | Change Manager- Solman | Successfully tested | Logon to System | Successfully tested |
Released for Production | Authorized for Import |
Reset Status to "In Development" | In Development |
Go to Task Plan | Successfully tested |
6 | IT- Solman | Authorized for Import | Logon to System | Authorized for Import |
Import Correction to Production System | Production |
Reset Status to "In Development" | In Development |
Start Retrofit | |
Go to Task Plan | Authorized for Import |
7 | Change Manager - Solman | Production | Logon to System | Production |
Confirm Correction | Confirmed |
Reset Status to "In Development" | In Development |
Go to Task Plan | Production |
8 | Change Manager - Solman | Confirmed | Logon to System | Confirmed |
Complete Correction | Completed |
Reset Status to "In Development" | In Development |
Go to Task Plan | Confirmed |
Appendix E. Test Messages possible actions per status
Step | Who- Where | Initial User Status | Action | Final User Status |
1 | Tester- Solman | Created | Take "in Process" | In Process |
2 | Developer- Solman | Created | Take "in Process" | In Process |
3 | Developer- Solman | In Process | Logon to System | In Process |
Pass to "Retest" | To be Retested |
Create Transport Request | In Process |
Release Transport Request | In Process |
Create Task | In Process |
Go to Task Plan | In Process |
4 | Tester- Solman | To be Retested | Logon to System | To be Retested |
Confirm Correction | Confirmed |
Reset "in process" | In Process |
Go to Task Plan | To be Retested |
Appendix F. Administration Messages possible actions per status
See also these SDN Blogs:
- First steps to work with Change Request Management scenario in SAP Solution Manager 7.0
- Change Request Management scenario: Usual questions and known errors