Cut over activities

Former Member

Hi Sap Gurus,

Could you tell Cutover Plan & Activities in implementation.

with regards,

reddy

Accepted Solutions (1)

Accepted Solutions (1)

pankaj_singh9
Active Contributor

Hi,

Generally followed Implementation Activities:

TO Be Phase

As Is and To Be Documentation

Gap Analysis

To Be Sign Off

Closing of Gaps as per scope

Unit Testing

Preparation of test cases

Unit testing

Changes to configuration for any errors

Integration Testing

Integration Testing and Test Script Documentation

Indentification of Gap

Priortization of Gaps which are sure stopper for Go Live

Sign Off on Integration Testing

Closing of remaining gaps and processes

Basis Activities

List of Users for User Creation

Testing of Roles created for SMB Proejcts on ECC 5.0

Ensure Availability of PC with SAP Front end, LAN, Printer at each required end user place at all locations

Front End loading and Testing of SAP transactions at each locations

Completeness of Connectivity between HO and other locations.

Strategy for Authorization Profile, roles and User Creation

Testing of Authorisations

Client Copy from Dev to Quality & production / New Client Preparation

Master Data Activities

Preparation of Master Data

Validation of Master Data by Bcone Team and Core Team

Sign off on Master Data Prepared

Preparation of LSMW for Master Data

Preparation of BDCs for Specific Master Data

Test Upload on Test

Upload of Master Data in Sequence on Test

Cutover Activities

Communication to Vendor, Customer and Excise etc

User Training by Core Team

Cost Roll ups and Validations - Test

Upload of Master Data in Sequence on Test

Start entry of Open Sales Orders, Quotation, Enquiries, Purchase Orders in Prod

Stock Taking Activity at Plant

Stock Upload with SAP Material Code, Qty, Value and Storage Location as on Go-Live Date

Enter Cash Balances as of Go-Live Dates

Enter Excise balances as of Go-Live Dates with monthly duty payment for March

Configure Cut off Excise Number Range (Excise Invoice, RG registers) as on Go-Live Dates

Back up of Loaded Production Server

Go Live

Availability of all balances

FI Balance uploads (For both ledgers/ subledgers/ assets/ customers/ vendors)

0 Kudos

This message was moderated.

Answers (2)

Answers (2)

Former Member

Hi

Cutover is The process of transitioning from one system to a new one

Cut over Plan is All documentation related to planning, preparing and executing cutover, describing how to lock down the system from a technical change management perspective, preparing the the system for its new role and rolling out the SAP graphical user interface to all future end users.

CUTOVER PLAN describes all cutover tasks that have to be performed before the actual go-live

Examples of cutover tasks are:

Review and update all systems-related operations procedures like backup policies and system monitoring

Assign ownership of SAPu2019s functional processes to individuals

Let SAP AG do a GoingLive check, to get their blessing to go live with the system

Lock down the system, i.e. do not make any more changes to the SAP system

Planning the Master data Migration Process is also a Cutover Task.

Thanks & Regards

Kishore

former_member192897
Active Contributor

Cutover Activities or Master Data Uploading Strategies Depending upon the when we are going live. As per that, you have to give the information to your core team. If you goling live at the middle you have to upload the all P&L Account items and B/S Items. If you going live at the financial year start, you have to only Upload the B/S Items. Activities for Golive:

1. G/L Master Upload Thru BDC or LSMW (TC-Fs00 and extended one co code to another company code Fs01)

2. Vendor Master Upload Thru BDC Or LSMW (Will be Taken Care By MM)

3. Customer Master Upload Thru BDC or LSMW (Will be Taken Care By SD)

4. Asset Master Upload(Thru As90)

5. Cost Element Master Upload

6. Cost Center Master Upload

7. Profit Center Master Upload

8. G/L Balances Thru F-02

10. Vendor Balances thru F-43

11. Customer Balances thru F-22

12. Customer Advances thru f-29

13. Vendor Advances thryu F-48

Before uploading Vendor Balances you have to take care of WHT(TDS) Information.

Regards,

Ashok