Hi Gurus,
We have a customized logic (special batch numbering) on conversion of planned orders to process orders. In the ECC side, if we convert planned orders to process orders, this logic is being applied. But if we convert the planned orders to proc ord at the APO side, this logic is not applied.
Which program/transaction does it use when converting planned ord to proc ord? Any suggestion? Thanks
Kumar
hi
the customized logic is in R/3 not in APO.
better post the issue in APO forum
-ashok