Dear All ,

We have activated release strategy for scheduling agreement .Previously while maintaining schedule lines it was not going for release .

But now while maintaining schedule lines in ME38 it is going for release .I want to know what is the reason and I want to stop this .

We have made some changes in Closed PO amendment ,like we have changed the release indicator value R -6- 10% to R - 6 -0% .

Like whenever we make change in price of a PO even a 1paise

it should go for release .

The release strategy for SA and PO is same .

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Since you have changed the release indicator it is again going for release for any change.

Please change the release indicator to 2 from 6 so that you can change the schdeule lines or any modiifcation again release will not set

Please check the release indicator in P.O and SA

G.Ganesh Kuamr