Hi,

How batch determination can be done automatically for components in process orders?

regards,

Mohit Goyal

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi Sravan,

Thanks for responding.

Is it possible to do automatic batch determination at the time of realease of process order i.e the batches of the components are automatically determined in the process order/

If yes, then please suggest what are the settings?

regards,

Mohit

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Go to the MRP2 view of material master 3 Automatic batch determination upon release of order.

Please refer my previous posting for Batch determination for Process order and componenet.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Sravan,

Is it possible to determine batches for components in process order upon saving only i.e before release of process order is carried out.

regards,

Mohit Goyal

Former Member
0 Kudos

In the Material master MRP2 select the batch entry to 1.

In this case until you do the batch determination for production order system will not allow release of production order.

But as per my knowledge we cannot do automatic batch determination during order saving.

Kindly revert back if any queries.

Former Member
0 Kudos

In SPRO

Maintain batch search procedure for Process orders.

Follow all the steps in the batch determination in SPRO

then you can get automatic batch detemination.

In Material master MRP-2 View select Batch entry to 3.

Kindly revert back if any qureies.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Define the batch determination search strategy for process order in COB1 with sort rule in CU70.

On the initial screen of your application choose Logistics>centrel function>batch management>Batch determination>For process order -->Batch search strategy --> Create.

On the initial screen of your application choose Batch search strategy -->Create.

Choose the strategy type, say choose co02

Choose the key combination-

Enter the required dat-->say plant ,production order type, product,valid from and component for which you want to have this

Choose Selection criteria push button. Choose a sort sequence.

If no values have been entered, enter the selection class and the characteristic values.

Go back to the screen on which you create a batch search strategy.

Choose Sort if required(it should be defined earlier(in CU70- here you are giving the charateristic name on which you want to sort)

For component you need to use MBC1 with search stratgey as ME01 for your plant movement type and material and assign the sort rule and search procedure here.

Check also in COR4, for the combination of plant and order type...you have selected search procedure-CO0001

Batch management> Batch serach procedure allocation and check activation

T.Code to be looked specifically OMCG , CORC

Hope it will help you.

Regards,

R.Brahmankar

Edited by: R Brahmankar on Nov 11, 2008 11:31 AM

Former Member
0 Kudos

Hi,

You can maintain automatic batch creation in :

CORY->Select Plant & Production Scheduling Profile->Batch Management->Auto Batch Creation->Select

1.Automatic Batch creation at order creation

or

2. Automatic Batch creation at order release

Hope this helps.