on 12-10-2008 8:17 AM
"Scrap Generated' col is not getting updated after reconciliation.
The waste that is generated during the process of subcontracting. This is mentioned as the percentage of process scrap in the bill of material of the parent material against the child material.
Hi:
In J1IFQ you won't get any option to enter the scrap quantity it is is greyed out.
This is because yuo must have defined scrap in BOM,so while reconcillation system would consider the quanitty less the scrap amount generated.
Cheers
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
while reconsiling the SC challan by J1IFQ u mention the scrap QTY or if already done, try with J1if11
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.