Reservation for components

Former Member
0 Kudos

When i create production order dependent requirement for components will be converted into reservation.

How to have setting which will convert all dependent requirement into reservation when production order is released.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Mr. Paresh,

In OPL8 - Planning tab set the Reservation/Purch.Req. field to 2. This might work in your case.

Regards,

Subha.

Former Member
0 Kudos

Hi

Thanks for your reply.

But after making those settings result is same that reservation are creted when production order is created.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please refer this thread,

Try with new order.

Regards,

R.Brahmankar

former_member184655
Active Contributor
0 Kudos

Dear Paresh naik,

I could not understand what's your problem,check in T Code OPL8 for each order type under

implementation tab key for reservation.

Regards

Mangalraj.S

Former Member
0 Kudos

I want to generate reservation for components when production order is released and not when production order is created.