When i create production order dependent requirement for components will be converted into reservation.
How to have setting which will convert all dependent requirement into reservation when production order is released.
Dear Mr. Paresh,
In OPL8 - Planning tab set the Reservation/Purch.Req. field to 2. This might work in your case.
Regards,
Subha.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Paresh naik,
I could not understand what's your problem,check in T Code OPL8 for each order type under
implementation tab key for reservation.
Regards
Mangalraj.S