on 01-18-2009 4:28 PM
Hi,
Scenario:
MTO strategy
We have one operation is subcontracting. When we take MRP run all PurReq. & PLOrd are reference to sales order. But when we want to transfer material to subcontractor through TCode MB1B Mvt type 541 that time system issue the following message.
Deficit of SL Unrestricted-use 3,150 KG : 119 1002 RM
Then we have to transfer stock reserved against sale order to unrestricted.
Requirement:
Can we transfer stock to subcontractor with reference to sales order.
Pl tell me how I resolved this issue.
Thanks & Regards
Dhamane
HI if you have reserved the stock against the sales order and now you plant to make use of that quantity then you need to make use of the movement type 411 E to bring that reserved stock in your unrestricted stock and then you can make use that goods to issue to subcontractor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check OSS note 68908 how to handle components in SO special stock.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello....
You can not transfer material from Sales order Stock by movement type 541 as both stocks are Special stocks & has not recommend to transfer between two special stocks.
For this Solution , Transfer posting to transfer the provided components to a new storage location (for example, 9999) by using movement type 311. This enables you to obtain an overview of those stocks that are physically located at the subcontractor. This information is particularly important when you carry out a physical inventory of the sales order stocks.
Rajiv
Not Possible to Transfer sales order stock directly to subcontractor in Standard SAP.
First you need to Transfer Sales Order stock to Unrestricted using MB1B 411 E and then Transfer Stock to Subcontractor using MB1B 541.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In standard SAP only from unrestricted to unrestricted goods movement is possible between Plant's SLoc and subcontractor's special stock (by mvt 541).
So, as per my best knowledge you cannot move the goods from sales special stock...
Regards,
Csaba
Edited by: Csaba Szommer on Jan 18, 2009 10:12 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
Check whether setting MRP requirements as Individual requirements for this material rather than collective requirements. If the reservation for this material comes with sales order reference then you should be able to do that.
cheers
Rav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.