How to set DLV status for process orders in mass processing
Reagrds,
Amit
Hi Amit,
If the last operation in the SFO has PP03 control key, then mass confirm the last operation or order & DLV status will be set (use COHV)
Alternative use MIGO & post GR for all orders, the status will be set.
Hope the above is helpful.
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you let us know why you want to set DLV status w/o receiving the material into stock?
Added
You have marked the thread as answered, without providing any proper info or letting the forum know if the input provided was ok or not, nor awarded any points.
I am surprised by your attitude.
Edited by: Vivek on Feb 25, 2009 1:01 AM
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.