Subcontracting order

Former Member
0 Kudos

Hi,

We have one reservation for a material (BOM component of a Purchase order item) was originally created via a subcontracting PO. Then deletion indicator was set to PO line item. Then the component assigned to PO line item was deleted. But now we can not delete the reservation.

If you have faced similar situation, could you please suggest me how delete the reservation(identified as Subcontract Requirement in MD04) in this case?

Thanks and Regards,

Nataraj

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

What is the error you are getting while trying to delete the reservation

Former Member
0 Kudos

Hi ,

We have faced a similar situation wrt to Sales order and Production order where the dependent reservations were seen in MD04 after the deletion of sales order and also the TECO for production order .

Try using MBVR / mb22 and check , if not OSS would be the approach .

Regards

Lokesh