Hi All

In my PO release for a particular strategy having five levels of release , when the PO is released till 4th level automatically it's Release Indicator is changing to "C" i.e completed whereas it should happen when PO is released for 5th level i.e final release.My PO release strategy is not having any release pre-requisites i.e it can be approved any level at any point of time.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

If you don't have release pre-requisites, then where you have defined the order of release ?? Normally we use to give order of release in release pre-requisites. According to that the document will be released.