Cost is not matching in Report
S_ALR_87013532 & It's drill down report sum.
Same is case for Table RPSCO & COEP for particular project.
Nopt solved even after running CJEN.
Please guide.
SSanjay
Solved.
Run CJVC.
Value Category Customising & Assign Cost ELements to it.
SSanjay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check whether you have made Account Assignment for only lowest level WBS.
Also check whether you have made any postings to only lowest level WBS.
If not , then system is showing correct values.
Consider following eg.
your plan and actuals values are
level 1-WBS A = 100
level 2 -WBS B = 100
level 2- WBS C = 100
but in report header level it will show 300 instead of 200 i.e B+C.
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I understand at Level 1 WBS, system shows costs of Level 1+ Level 2.
This is not case here.
Cost shown in Report S_ALR_87013532 is 2,087,275.
Which is not correct because we know this project has already postings, booking.
Project worth 50,000,000 is half completed.
Cost should be more than 10,000,000.
Also cost shown in drill down of S_ALR_87013532 is 12,390,427.
Which looks more correct.
Why is the difference?
Please guide.
SSanjay
Please Elaborate your problem...What are the values u r getting in diff reports...and which report shows the right value...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.