Hi

Is it assignment of Purchasing org to Plant mandatory?

Why it is mandatory?

Raju

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hI,

Assignment of Purchasing org to Plant is mandatory without which you can not carry out procurement activities for a plant. Assignment of P.org to company code is optional, not mandatory.

REgards

Ram

Former Member
0 Kudos

Its not mandatory.

Its depend upon your requirement only.

Whether you want central Pur Org.

Plant specific Pur org.

Prashant

Former Member
0 Kudos

Hi

I am planning to use for all plant under one company code, then is it required?

Raju

Former Member
0 Kudos

Hi,

Then you assign all plants to your P Org. This assignment is must. You may assign Porg to your company code or not.

If you don not assign P org to company code , while creating PO you have to enter the company code.

REgards

Ram

Former Member
0 Kudos

Hi

ok, Is it possible to assign one plant to 2 purch Orgs?

Raju

Former Member
0 Kudos

Hi,

Yes, you can assign.

Regards'

Ram

Former Member
0 Kudos

U can assign one Plant to many P org

Amit