confirmation operation time to be displaysd when it comes in betwn holidys

Former Member
0 Kudos

i am doing one confirmation ( co11n ) which started on saturday 17:30 pm but the wrkcenter timings are

9:00 am to

18:00 pm but the operation time is of 4 hours 0:30min on saturday and remainig balance on monday with 3hr

30 min done but in my confirmation startdate is on saturday ( 23/05/2009 ) , 24/05/2009 is sunday and end

on 25/05/2009 but my client want time required to complete the operation i want to get only 4 hours but when

i see the difference between start and end it is showing sunday also to get 4 hrs where can i see the time

completed operation in the report.

regards,

muralidhar.t

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

it was a good help

rohit_chauhan
Contributor
0 Kudos

Hi Muralidhar,

You can get the deatils from the COOIS report.

Choose Operations - Standard Layout, then change the layout and add columns Activity 1 to Conf., its unit. Similiarily add other activities too (as many you are confirming in CO11N).

In the CO11N screen, enter the actual setup, processing times etc, you will get the actual values in COOIS then. Then you wont require to subtract the start date and time from finish to get the operation time details. Moreover these values are only for start and finish times not the operation time or activity time.

Your operation started on saturday and ended on sunday, but actual operation time will be shown in activity time entered during confirmation.

Hope that helps.

Regards,

Rohit

Edited by: Rohit Chauhan on May 27, 2009 9:13 AM

Former Member
0 Kudos

sir,

would u please tell me in which table the actual start time and actual end time will be saved and i want to know the difference between start and end time which it must exclude sundays and public holidays . so please hlep me sir.

regards,

muralidhar.t

rohit_chauhan
Contributor
0 Kudos

Hi Muralidhar,

Check the table AFVV. It contains the Actual & Planned dates.

Regards,

Rohit.