on 07-04-2009 10:03 AM
Dear All,
What is cut over purchase order?Can you elaborate all types of purchase orders?
Hi,
Cut over PO are not any std PO document type.....
Before Going Go-live, there is a cut over plan and stretagey. In this Time frame consultant upload master data, open PO etc in production client.
So Cut over PO are PO uploaded before Go-Live.
Hope Clear U !
Regards,
PArdeep Malik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Let us say u r going live (in SAP)on 6th july
Today is 4th july.
There must be some open POs in legacy system.
These open PO need to be moved to SAP.
These are cutover POs
Thank You
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
Cutover PO are the open PO to be carried forward from legacy to SAP ...its just a naming convention ...
u can call it legacy PO also
You are talking about a document type for PO given name "cutover"... which u can see in ME21N ....
ur consultant must have made a document type with name "cutover PO" for making cutover PO.. of legacy.... to help in tracking of legacy PO
Thank You
User | Count |
---|---|