Hi everyone,

Here they have created list of GLs for a project both billable and Non-billable items my dought is where we are assigning this GLs

in Spro. so that it automatically updates..

Please help me

Thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Any entry can be posted to GL accounts with the cost object WBS element. You will be able to plan and budget for these cost elements for a particular WBS element. For this, if you go for planning and budgeting for the WBS element, all the cost elements will appear and there is nothing to be configured specially. On the other hand, there are some GL accounts which needs to be configured as the Settlement receivers for the Projects in SPRO.

Regards,

Lakshmanan Krishnan

iklovski
Active Contributor
0 Kudos

Hi,

There is no such a thing as assignment of G/L to PS objects. The actuals when posted to G/Ls could be 'linked' to certain WBS as additional account assignment.

Regards,