Delivery date for Non stock items

Former Member
0 Kudos

Hi,

While creating Maintenance order for Non stock items in component screen planned delivery time fld comes. Here

I put 10 days. But system creates PR with delivery date as today's date ie order creation date.

Actually delivery date should be 20.09.2009.

Waiting for your valuable inputs.

Thanks

Prasad

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Prasad,

The planning Delivery Time is not consider what you giving in Order, system only taking from master data i mean in material master

so you have to mention in Planned delivery time in Material Master then system automtically taking to delivery date relevant to that date plus current date

befor doing check info record Planned delivery date also, system also consder this also

Hope this may helps you

Prem.

Former Member
0 Kudos

Dear Prem,

In mat master plnd delivery time is 30 days & GR processing time is 3 days.

For the same material if i create PR from ME51N system shows Delivery date as 12.10.2009

For the same material if i create PR from IW31 system shows del date as 11.09.2009 ie today's date

Kindly says where i'm going wrong. Is there any config from PM end?

Thanks

Prasad

paul_meehan
Employee
Employee
0 Kudos

Hi,

The requisition delivery date is dependent on the operation start date. System does not consider the planned delivery time when calculating this delivery date.

The delivery date is based on the following calculations:

- The start date of the operation

- Minus Goods receipt processing time of the component

- Plus or Minus Lead time offset for the component in the order

The above values can be adjusted to manipulate delivery date.

As mentioned, It is also possible to influence this date by implementing exit COZF0002.

-Paul

Former Member
0 Kudos

Thanks paul

Prasad

Former Member
0 Kudos

Hi,

Check to recalculate the delivery date using user exit :-

COZF0002 Change purchase req. for externally procured component

regards

pushpa