Dear Experts,
In our organization planned orders are getting generated through MD02 for a particular plant, but not getting generated through MDBT.
Please suggest what could be the reasons.....
Rgds
Hi ,
Usually the cause is that the corresponding planning file entries are not set for the material (transaction MD21). You can find further information on planning file entries in notes 205681, 371016 and 553746. In order to check which materials the total planning run plans, it is recommended that you set the 'Display material list' parameter in the planning variants. The spool list for the job then lists the planned materials.
Regards,
Anupam