on 09-25-2009 8:05 AM
Hi Experts,
I am planning to extarct Palnned Cost from R/3 , which one should i cosider among 0CO_OM_WBS_1, 0CO_OM_WBS_3.
what is the dfference between these two data sources.
Thanks
Bhanu
0CO_OM_WBS_1 DataSource provides all costs and quantities (plan, actual, and commitment) of the WBS element.
0CO_OM_WBS_3 DataSource provides the plan costs for the WBS element that were planned in the hierarchy.