Release procedure for PO

Former Member
0 Kudos

Hi,

I have created Release Strategy for PO it is working fine till first time releases, now after release if I make any changes in that PO again release strategy must get triggered, but in my case it is not working, so what settings to be done to solve this problem

Thanks

mmsaperp

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Check the Release indicator in your release stratergy.

Set the Changeable indicator (4 or 6) as per your requriement in the release indicator.

Thanks & Regards

Karthick

Answers (3)

Answers (3)

former_member210560
Active Contributor
0 Kudos

Dear mmsaperp,

The release strategy will only reset when your PO's total net price had been increase during changes

and if another release strategy criteria now met your PO. If you want any change with any fields, the strategy

get reset, then this not available in customizing but with system enhancement with Enhancement M06E0004,

EXIT_SAPLEBND_002 where you can write your own code.

Best Regards,

Ian Wong Loke Foong

Former Member
0 Kudos

Hi

In standard SAP only if you change the value(net price) the release strategy will be reset ,this can done in the path

spro-material management -purchasing -purchas eorder-release procedure for po-release indicator here you have a column percentage value change ,input the percentage for which you need the release strategy to be reset .

note:In my current implementation we had the requirement very similar to yours ,what we have done we had written a code in a user exit

Regards

Sandeep

Former Member
0 Kudos

Dear,

Mainatin Changeability of Purchasing Document During/After Release as per your requirement in release procudure>release indicator.

Regards

Subhash