on 11-23-2009 7:11 AM
Dear All,
I gave 24 Hrs clock in Capacity tab of work Center, with 3 Hrs break, and available capacity as 18 (labor) for 3 shifts.
Operating time 16.80
Capacity utilization 80%
No. of indiv. cap. 18
Available Capacity 302.40 HR,
When I Run MRP with u201CLead Time Scheduling and Capacity Planningu201D,
For Order Quantity 16 Pc, I get scheduled Time as 256 Hr, and Planned dates over above 10 days.
When I check Capacity on work Center in CM01, it shows 16.80 Hrs as Capacity Req.
And 302.40 Hr as available capacity, so it consumes only 5%. And the dates are as over a week. No Other Orders are booked over this work Center,
In Routing the time given for one article is processed by 2 labors for 8 hrs , hence 16 Hrs, as system calculates 302 Hrs of capacity available,
Please tell me where am I going wrong,
My available capacity is 302 hr
And System only picks up the clock time of operation in capacity req. i.e. 16.80 hrs.
Please suggest
Regards
Raghu
Closed !
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.