Capacity Req. not showing as it is.

former_member228481
Contributor
0 Kudos

Dear All,

I gave 24 Hrs clock in Capacity tab of work Center, with 3 Hrs break, and available capacity as 18 (labor) for 3 shifts.

Operating time 16.80

Capacity utilization 80%

No. of indiv. cap. 18

Available Capacity 302.40 HR,

When I Run MRP with u201CLead Time Scheduling and Capacity Planningu201D,

For Order Quantity 16 Pc, I get scheduled Time as 256 Hr, and Planned dates over above 10 days.

When I check Capacity on work Center in CM01, it shows 16.80 Hrs as Capacity Req.

And 302.40 Hr as available capacity, so it consumes only 5%. And the dates are as over a week. No Other Orders are booked over this work Center,

In Routing the time given for one article is processed by 2 labors for 8 hrs , hence 16 Hrs, as system calculates 302 Hrs of capacity available,

Please tell me where am I going wrong,

My available capacity is 302 hr

And System only picks up the clock time of operation in capacity req. i.e. 16.80 hrs.

Please suggest

Regards

Raghu

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member228481
Contributor
0 Kudos

Closed !