on 12-04-2009 11:04 AM
Hi All,
What is the procedure to change the Unit of Issue of a material where as material document has created for goods receipt and goods issue.
Santosh
Dear Santosh,
Use the transaction MM02 Select view (Plant Data / Storage 1) Put Unit Of Issue it will allow if mvt. done for the material.
Regards,
Manish Jain
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Try defining UNIT OF ISSUE as alternate unit for Base UOM with relevant conversion factors. Then include unit of issue in material master. I Hope there will be no problem in this procedure even if you have previous material movement documents
Regards,
Syed Husain.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.