hello SAP Gurus,

 

while creating workcenter in basic data if you select standerd value key SAP1 you will get standerd values setup,machine & labour. now when we go to capacity tab we get there field setup formula,processing formula & teardown formula now my question is. Is this mean that setup=setup formula, machine=processing formula & labour=teardown formule please tell me whther i am wrong or right?

 

regards,

dev123.

  • Re: Work center
    Sundaresan Velayudam
    Currently Being Moderated

    Yes,

     

    In OP55- we have to define the formula for all the parametersi.e how the capacity will calculate, here we have to define the formula Ex:  process time * operation quantity/ base quantity. in OP55 we have to tick for capacity requiremnt in Work center If the sameformula is used in Costing and scheduling , then we have to tick the concerned field in OP55.

     

    Regards,

     

    sundaresan

  • Re: Work center
    Anupam Sharma
    Currently Being Moderated

    Hi

     

    These standard values are not the formula for setup formula.processing formula etc, these are the operations or activities which are to be performed on this particular work center and this work center can be used as an operation in routing.These Values defined in SVK like SAP1 are used as formula parameters to calculate the setup time procesisng time and labour time on the basis of the base Qty for the routing which are defined in OP55.and these formula are used in scheduling the routing and then costing.

     

     

    I hope it is clear to you now

     

     

    Regards

    Anupam Sharma

  • Re: Work center
    KAUSHIK BASU
    Currently Being Moderated

    Dear Dev,

     

    Regarding the Work center formulae, first of all, you have to create various parameters (viz. Setup, Machine, Labor, etc.) using OP17. Then, you need to customize the Standard Value Key formula in SPRO transaction: OP19.

     

    Lastly, create the formula definition in OP21.

     

    These will be picked up in your work center.

     

    Hope it helps.

     

    Regards,

    Kaushik.

  • Re: Work center
    Rupesh Brahmankar
    Currently Being Moderated

    Dear,

     

    Yes setup=setup formula, machine=processing formula right but labour not =  teardown formule.

     

    Capacity category      001       Machine

     

    Setup formula        SAP005    Prod: Setup rqmts

    Processing formula   SAP006    Prod.: Machine rqmts.

     

    Then Create Another Capacity Category as 002 as labour (Header menu Edit--New entry)

     

    Capacity category      002       Person

     

    Setup formula        SAP005    Prod: Setup rqmt

    Processing formula   SAP007    Prod.: Labor rqm

     

    Regards,

    R.Brahmankar

    • Re: Work center
      devaraj nikam
      Currently Being Moderated

      hello Bhramankar Sir,

       

      thanks for reply but if we mentain both machine & labour categary in capacity view then what about schduling view does it consider both capacity catagarys. if i want to use setup, machine,& labour also then how can i do that means in schduling & also in costing view which farmulas i have to use?

       

      regarda,

      dev123.

      • Re: Work center
        Rupesh Brahmankar
        Currently Being Moderated

        Dear,

         

        Labour is simultaneously working on machine while operation is performing on work center. In standard SAP we can schedule only one category. As machine is critical category we use it for scheduling. If you include the labour and machine time in scheduling then your operation time will be double than the required.

         

        Now coming toward the cost calculation as we define the second category as labour then system pick the formula for it and timing from routing and price from KP26 to calculate the Labour cost.

         

        In costing view of work center you need to use the formula ,

         

        SAP005 Prod: Setup rqmts

        SAP006 Prod.: Machine rqmts

        SAP007 Prod.: Labor

         

        Thake a costing run you will get the all these cost. it will also appear in your production order.

         

        Hope clear to you.

         

        Also check this link,

        Re: labour cost calculation

         

        Regards,

        R.Brahmankar