Dear Gurus,

We have implement item level PR release strategy,

characteristic used: 1. Document type, 2. PR item Value, 3. Material Group, 4. Change date & 5. Account Assignment Category.

BEfore the above implementation, there is a OLD PR release Strategy existing in the system at one level release.

Now the issue, the OLD release Strategy status is release completed, now the user goes and change the PURCHASING GROUP in old PR, new release gets triggered. How to Stop this, system should not trigger NEW STRATEGY,

Please advice

REgards

RS

Accepted Solutions (0)

Answers (2)

Answers (2)

mohd_uzairhussain
Contributor
0 Kudos

RS

Please check if this works in your case !

After configuration of new release strategies if u dont want any impact on Older ones then add CREATION DATE of PR as characteristic and key in value for it as >= date of new changes/ new strategies moved to PRODUCTION system.

I think this works, check in ur DEV system and lets know

Regards,

Uzair

Former Member
0 Kudos

Not something I've ever done/seen but presumably if the new release strategy criteria apply to an 'old' requisition, then that's your problem.

You could try adding the date created as one of the classification criteria and set to greater than or equal to current date

Former Member
0 Kudos

HI,

If i use date created as a characteristic, then Old release strategy get reset and the no release strategy will be trigger henceforth, the status of the PR will be INACTIVE.

ANy charateristic we use, there will be only 2 options for old released PRs, 1) It will reset the strategy to new one or 2) the old strategy will be reset and make the PR status as INACTIVE.

Is this is standard behaviour? pleae advice

Regards

RS

Former Member
0 Kudos

Yes, this is std behaviour.