Hi Kenneth,
Each operation has different resource and order is getting scheduled for multiple days. As suggested by you , I can't use bucket offset or period factor. I need to calcualte the correct capacity requirment for all the operation and on the same day.
R/3 supports but SNP doen't support.
Instead of multiple operation, I'm creating multilevel BOM(dummy) to generate capacity requirement for all levels on same day. But system creates an offset of one day for each level of BOM. For example. If the FG required date is on Friday, the first level component of BOM is scheduled for Thurdsay. The second level component is scheduled for Wed and so on.
I have set the proper lead time offset for the components in R/3 BOM. Is there any other data we need to setup?
We are on SCM 7.0 and we are using PDS.
Thanks
Ravi