Dear gurus,

i find in the material master (MM02 and in the table MARA) the parameter "Low-level code" = 000 , how use this parameter ?

When this value is write? At saving of Bom? Is a setup of customizing for value possible?

Thanks a lot

Daniele Pistilli

PP TEAM

Accepted Solutions (0)

Answers (3)

Answers (3)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Depending upon the BOM structure, System will automatically assign the low level code.

You can see it in Material Master, Information (Blue Button).

Please refer this link,

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi

I think u have got the answer , pl close the thread

Ram

Former Member
0 Kudos

Hi

Pl go thru the following may be useful

The lowest level that a material appears in any product structure of the

company. The low-level code controls the sequence in which the material

is planned in an MRP run: First the materials with low-level code 0 are

planned, then the materials with low-level code 1, and so on. The lower

the low-level code, the higher the number that is assigned to the

material.

The level that is set in the material master record represents the level

at which the material will be planned. This means that the material will

only be planned once all assemblies in which it occurs have been planned

and exploded.

The low-level code is set internally in the material master record when

the BOM is maintained.

When you create a bom item for a assemblyparts ,the item's low-level code will equal (assemblyparts's low-level code + 1),but if (assemblyparts's low-level code + 1) < bom item then the bom item's low-level code not changed

Ram