Hi All,

We have created release strategy for Purchase order more that value 250 GBP.

We have used user exit for overall limit value and invoice plan value means release strategy should trigger on these values.

Now release strategy execution is working fine while creating/changing the purchase order.

But when we use repeat output function (Transaction: ME22N) and processed only repeat output not changed any other field,

Release strategy again reset the previous release. (Release strategy tab disappeared from the PO).

We donu2019t want to trigger release strategy again while using only repeat output function in ME22N transaction.it should remain as it is.

Please Help ASAP.

Thanks in advance

Vikas

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Resloved, We have used userexit for release strategy, changed program.

former_member225662
Active Contributor
0 Kudos

Hi,

In PO , check the field Changeable under Release Indicator . Whether u201C 5 u201Cis there .?

The following here with is standard changeability indicator with description.

1 Cannot be changed

2 Changeable, no new determination of strategy

3 Changeable, new release in case of new strategy

4 Changeable, new release in case of new strat. or val. change

5 Changeable, new release if new strategy/outputted

6 Changeable, new rel. if new strat. or value change/outputted

Changeable, new release in case of new strategy

Path to check : SPRO > Materials Management > Purchasing > PO > Release Procedure for PO > Define Release Procedures for PO.