Hi Gurus,

Could u help me i am activated copa all sd delivery and billing document are flow values are properly but no single doucment was flow from PS to COPA..i have selected WBS element for costng and account based and i have done small configuration in IMG Flows of Actual Values,and Order assigned cost element and value filed Project Settlement, settement rule maintained

please help me

Regards.

Vinu

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

Have you done Settlement (CJ88) ?

Former Member
0 Kudos

Hi,

I have done CJ88. still value is showing consolidated....we are expected cost to be split ( Material cost and revenue separately

Regards,

Vinu

former_member203108
Active Contributor
0 Kudos

Hi,

HAve you maintained separate source and value field for materials cost and revenues...If you had grouped there, then you will get consolidated.

Former Member
0 Kudos

hi,

Thanks

Former Member
0 Kudos

Hello,

Also check the KE4R and KE4S to assign material and activity with cost component.