Release strategy

Former Member
0 Kudos

Hi,

We are using PO release strategy using classification .

Any change in value after PO approval need to reset the release strategy

We are using Changeability of Purchasing Document During/After Release indicator 6 with zero dollar value .

But still it is not resetting the approval process .

Thanks

Nic

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

First of all it is not resetting the release strategy , Second any change in price , we are fine with higher value also.

Do we need to change the Output or call any user exit ?

former_member225662
Active Contributor
0 Kudos

HI,

Try this link

Regards

KK

former_member225662
Active Contributor
0 Kudos

Hi,

Reset of release strategy will take place if:

- the changeability of release indicator is set to '4' in PR or '6' in case another purchasing doc (PO, RFQ, contract, scheduling agreement).

- the document is still subject to the previous release strategy

- the new TOTAL NET ORDER VALUE is to be higher than the old one.

Also check sap notes 493900

Regards

KK