Hi
I am facing issue in Material availability date.
I guess this should match with Proc. Order finish date , pl. guide or How MAD is linked others.
Dear ,
In Material Availability Date for External Item is calculated based on the Plnned delievery Time and GR processimng Time in Material amster .
Material Availability Date =PR Creation Date +Releasing of PR Time +Planned Delievery Time +GR processing Time
Please try one example in sandbox and revert
Regards
JH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
dear friend, i am not sure what you're after...just some tips helpful for you
Example of Forward Scheduling for External Procurement:
Material shortage date plus processing time for purchasing plan plus planned delivery time = delivery date
01.08. (Friday) plus 1 workday + 10 calendar days = 14.08. (Thursday)
Delivery date plus goods receipt processing time = availability date
14.08. (Thursday) plus 2 workdays = 18.08. (Monday)
Example of Backward Scheduling for In-House Production:
Requirements data minus goods receipt processing time = order finish date
25.6. (Friday) minus 2 workdays = 23.6. (Wednesday)
Order finish date minus in-house production time = order start date
23.6. (Wednesday) minus 6 workdays = 15.6. (Tuesday)
Order start date minus opening period = order opening date
15.6. (Tuesday) minus 6 workdays = 7.6. (Monday)
also have a look here:
Example for Determination of Availability Date
http://help.sap.com/saphelp_47x200/helpdata/en/25/62f3135b3811d1a62f0000e83235d4/frameset.htm
good luck
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.