on 04-14-2010 12:49 PM
Dear Experts
Is it possible to track the history or updation of component tab in PM order. I have checked in change document for orders but it is not showing first component added. it only records if we change the quantity,
The requirement is that it should update action log as well in change document for work order when ever we add , delete or update the material in component tab and in the same way for PRT also.
The following setting I have done
SPRO>Plant Maintenance and Customer Service>Maintenance and Service Processing>Maintenance and Service Orders> functions & settings for order types--->Define change Docs collective purc req Indicator , operation no interval
Here I have checked both boxes for materail status change document as well as PRT status change document but still it is not updateing in action log and change document.
Regards
Vishvesh
There are seperate check boxes for Material change doc and PRT change doc along with Order change doc. Have you activated all of them??
Sarang
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Yes I have activated those check boxes but still action log & change documents are not updateing
The following setting I have done
SPRO>Plant Maintenance and Customer Service>Maintenance and Service Processing>Maintenance and Service Orders> functions & settings for order types--->Define change Docs collective purc req Indicator , operation no interval
Here I have checked both boxes for material status change document as well as PRT status change document but still it is not updating in action log and change document.
Regards
Vishvesh
Hi
Yes I have activated those check boxes but still action log & change documents are not updating
The following setting I have done
SPRO>Plant Maintenance and Customer Service>Maintenance and Service Processing>Maintenance and Service Orders> functions & settings for order types--->Define change Docs collective purc req Indicator , operation no interval
Here I have checked both boxes for material status change document as well as PRT status change document but still it is not updating in action log and change document.
Regards
Vishvesh
Hi,
The change documents / action log will only show details for component changes. The create/delete function will not be visable in detail, you will only see a insert RESB and delete RESB entry in the change documents log.
Deletion of component - once the order is released the component is not physically deleted at table level but is hidden from view. You canuse the option Edit - Display Deletions - On to see these components.
-Paul