Hello friends,
i have an issue in which, i want to restrict the purchasing people to make a PO which crosses the P.req. quantity.
Please suggest.
thanks in advance,
Regards,
YK
Edited by: 1234_abcd on Apr 17, 2010 12:04 PM
HI,
Set the message no.076 in apll area.06 "materials of requisition already ordered in full" to Error msg
please award points if helpful.
Antony anburaj wrote:>
> HI,
> Set the message no.076 in apll area.06 "materials of requisition already ordered in full" to Error msg
>
quote}
We applied this solution as well. Best solution for this situation
If any warning coming for ecxeed- make it Error
Hi,
This message 06 76 will restrict the Po qTY > PR qty..
But this doesnot work for service PR and Service PO.
Raheem
Go to transaction OMET
Click on “New Entries”.
Enter the following values as shown below:
Function authorisation: restrict qty of PO to PR
Field selection: me21
click on adopt PO price
Save your entries.
Now we need to assign this function to the corresponding end users. Go to Transaction SU01 OR SU52 -> Click on tab “Parameters”. Maintain the parameter EFB.
Now we need to set an error message when the end user tries to create a PO greater than PR.
Click on System messages.
Click on “New Entries” and create the following entry.
Save and Exit. Now whenever the end user tries to create a PO with quantity in excess of that in PR, then the above error message would appear. If you just want a warning message to be shown, change the message category to ‘W’.
Thanks & Regards
Vikas Pawar
SAP MM Consultant
Larsen & Toubro Infotech Limited