Hi Experts,
I have scenario where bottleneck resources changes with time. Lets say that I have two workcenters WC1 & WC2. Operation 10 will be performed through WC1 and operation 20 will be performed through WC2. SFG1 is input material for operation10 and FG1 is output material through WC2. So SFG1 will be processed through WC1 & WC2 and output material is FG1. Operation 10 & 20 are sequential operations. WC1 & WC2 have the same scheduling time for both the operations 10 & 20
Now, WC1 runs in three shifts in May'10 and WC2 runs 2 shifts in May'10. So WC2 is bottleneck resource in May'10. In June'10 WC1 runs in two shifts and WC2 runs in three shifts so WC1 is the bottleneck resource in June'10. Simply, bottleneck resource can be either WC1 & WC2 depends on time.
So in my routing I have two operations and operation 10 contains WC1 & operation20 have WC2. Further, we created Production Version (PV) and CIFed as PPM. When converting PP/DS PPM to SNP PPM I can chose only one mode so only one work center (resource) in one PPM and another work center in another PPM. We need both workcenters in one SNP PPM.
Could any one guide to meet this scenario.
Thanks,
Naveen
Edited by: Wilian Segatto on May 14, 2010 11:54 AM