Hi
1.Stores material issued towards vendor which can be deducted from his invoice.
2.Vendor involves in a activity/work
Eg. Construction
3. Cement bag cost should be bare by vendor, but he avails it from stores, which can be settled against his bill
Question
1.How to capture the goods issue in MIGO to control the vendor invoice.
Note : Vendor is one time.
Please guide.
Regards
Sr
It not clear ? Why u give mat to venmdor . Iis it Subcontracting Process .If not proceed as follows
U need to create the vendor as a customer , Do delivery and PGI, Bill the customer , and when customet gives the amout , clear the customer .
OR
1.Stores material issued towards vendor which can be deducted from his invoice.( CREATE SEPERATE CR MEMO FOR THE SAME - INVOIVE POST AND CREATE CR MEMO)
2.Vendor involves in a activity/work
Eg. Construction
3. Cement bag cost should be bare by vendor, but he avails it from stores, which can be settled against his bill
Question
1.How to capture the goods issue in MIGO to control the vendor invoice.(CREATE RETURN PO - ITEM TICKED RETURN, DO MIGO -161 MVT TYPE , cr memo)
Note : Vendor is one time.
Please guide.
Regards
Sr
rewdzzz
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kindly mention the scenario in sap with document flow ,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For eg. We are out sourcing the construction of a lab to a contractor.
contractor agrees to construct the lab for rs. 10k. including material.
if he uses our cement bag... then the cost of the cement bag can be deducted from his bill (10,000 - 250)
.....
Pl advise the document flow so as to control the vendor invoice.
regards
Sr
It is a subcontracting Process ?
Its mm cycle - create Subcon PO with itel L . with seervice cost -maintained in item (cement price + service cost)
GI to vendor 541
do Migo 101 and 543 -(consumption of cement used - automatically comes)
IV the Vendor - contractor
Payment to vendor
pre req: is BOM maintained
if excise req: create challan config - since u issue cement excisable mat out from ur plant to vendor - challan is req.
consult an MM consultant there and suggest the same with meeting together with user/MM/S/Project maanger - do a good process and make it go live . cheers
rewdzz
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.