on 04-30-2010 10:44 AM
Hi all,
While doing MRP for WBS through MD51 i have got an error " No reservations relevant to MRP exist for project " . I am not getting where the problem is occurs.
Regards,
Swapnil Vaidya
Dear .
1.Please check wether in your project builder(CJ20N) Project Status is REL and Procurement Type is :Reservation for WBS element . then it will not create this masg.
2.Check whether MRP run date is after the project start date as well as the WBS element is also with in the time frame
3.Check the material master parameters(MRP1-MRP4 view ) for Project material which are to be planned by that Project WBS .
Check and revert
Regards
JH
Edited by: Jiaul Haque on May 1, 2010 2:27 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Swapnil,
Have you finished creating planned order using MD51?
Me too getting the same error. If you have done,pls help me to do the same.
Thanks in advance.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Swapnil,
I am not good when it comes to Project stock. I am experiencing the same error when i try to generate the order report in Va03.
Do you know the solution for this. I think you had experience this error in the past. Thanks for the help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.