No reservations relevant to MRP exist for project

Former Member
0 Kudos

Hi all,

While doing MRP for WBS through MD51 i have got an error " No reservations relevant to MRP exist for project " . I am not getting where the problem is occurs.

Regards,

Swapnil Vaidya

Accepted Solutions (1)

Accepted Solutions (1)

former_member196530
Active Contributor
0 Kudos

Dear .

1.Please check wether in your project builder(CJ20N) Project Status is REL and Procurement Type is :Reservation for WBS element . then it will not create this masg.

2.Check whether MRP run date is after the project start date as well as the WBS element is also with in the time frame

3.Check the material master parameters(MRP1-MRP4 view ) for Project material which are to be planned by that Project WBS .

Check and revert

Regards

JH

Edited by: Jiaul Haque on May 1, 2010 2:27 PM

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Swapnil,

   Have you finished creating planned order using MD51?

Me too getting the same error. If you have done,pls help me to do the same.

Thanks in advance.

Former Member
0 Kudos

Swapnil,

I am not good when it comes to Project stock. I am experiencing the same error when i try to generate the order report in Va03.

Do you know the solution for this. I think you had experience this error in the past. Thanks for the help.