Hello SAP Gurus,

We have a requirement wherein the client wants to know what is the correct way to move a cost element group (see KDH1, KDH2 and KDH3) to different clients and systems?

That is, how to make sure that the transport donu2019t overwrite the existing groups in production?

Thanks & regards,

Murali.S

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Murali,

Creation CE Group/ Change CE Group/Display CE Group : KAH1,KAH2& KAH3.

Follow below Steps for removing / Deleting Cost Element Groups.

1 - Remove Cost element assignments

2 - Execute T.cde:KSH3

Regards,

Viswa

anjireddy_appireddy
Contributor
0 Kudos

First we need to maintain connection and ALE rules between clients.

sap easy access-->Tools -->ALE -->Master Data Distribution -->Accounting -->Cost Element -->KAVC - Send Group .