In OME9 for K ,in I 1D-Acct assignment i have given value 2 instead of 1.What is the impact if i give this value?
Edited by: acapulcosdn on May 25, 2010 8:29 AM
Hi,
You can post to two different G/L instead of one.
Regards,
Biju K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Indicator: Account assignment screen
Indicates the standard account assignment screen used in account assignment maintenance for a purchase order item.
Procedure
If you enter 1, the dialog box for the account assignment of a single item will appear.
If you enter 2, the dialog box for the account assignment of several items will appear.
hi
if u have option 2 then u can have multiple assignmnet based on quantity and %
suppose u have item A with quantity 10
now u can assign 5 items for cost cenr X and 5 for CS Z
u have to create new line item with quantity 5
regards
kunal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.