on 06-09-2010 4:56 PM
Hi,
A service type SC is created with 2 line items in SRM 7.0.
The product category and accounting info is same for both items.
When this SC is bridged to R/3, the PR created has 1 line item and this line items has 2 sub line in service tab.
Is this standard SRM 7.0 functionality that for services, if the line item accounting and comm code(product category) are same the PR and PO will combine the like items?
How can we make 2 different lines in PR?
Richa
Hi Richa,
This is standard system behaviour. When a PR is created in R/3 with sevice items it will create one item. But within this item you will see all of your service items. It is like it is creating a container for the services.
It does not matter that the accounting is the same it will do this anyway. This is standard in R/3, SRM has no control over this behaviour.
I hope this clarifies what you are experiencing.
Kind Regards,
Lisa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Richa,
We have SRM version 7.0 .We are facing same issue of service line items combining in follo-on documents.
Can you please let me know where did you make chnages in code to fulfill this requirement? Did you make changes in any BADI?
Kindly reply.
Thanks & Regards
Vishakha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.