planned order splitting during capacity planning

bhakta vatsalam chadalavada
Currently Being Moderated

Hello,

anybody plese help me during the capacity planning in T.code.CM31 i want to split a planned order and want to assign alternative sequence. how can i do this and the capacity should be reschedule automatically to my requirement date. i am using backward scheduling.

plese suggest immediately

 

 

Thanks and reagards

Bhakta

  • Re: planned order splitting during capacity planning
    Jiaul Haque
    Currently Being Moderated

    Dear ,

     

    I am not quite sure whether you have option to change the Operation Sequence while dipsathing operation in CM31/CM21.You have option to change  Work Centre , Dispatch Date , Time , Hr etc  based on Strategy Profile configured at over all capcity profile -OPD0.

     

    But , you can have period split option based on the Operation Spilititng -Required Splitting is marked and actual number of split  is maintained in the routing operation .

     

    In Startegy Profile -Period Split -You can actuvate Always Adahere to period split and Operation Complete in Period Split , Start search in plan direct  then operation spliting required option will work .

     

    Selection of operation sequnece is controlled through order type .

     

    Hope it clarifies

    Regards

    JH

    • Re: planned order splitting during capacity planning
      bhakta vatsalam chadalavada
      Currently Being Moderated

      Hi JH,

      Thanks for ur reply. but i am not getting how to split. and second do you know i have maintaine alternative sequance. but i am not getting how to take consider this in MRP run capacity planning.

       

       

      Thanks & regards

      Bhakta

      • Re: planned order splitting during capacity planning
        Jiaul Haque
        Currently Being Moderated

        Dear Bhakta

         

        MRP does not perfom any Capacity Requirement Planning .While  you are executing MRP with Lead Time Scheduling , MRP proposes Planned Order Dates based on the Routing Operation Timing not based on the Work Centre available Capacity because in SAP Std R/3 we did not have scope to check the finite scheduling and capacity requirement chek .MRP assume that Work Centre has infinite available capacity .

         

        In MRP run , it will give you Detail scheduling of the Operation in Planned Order -Detail Scheduling tab  and copied the routing , BOM as master data .When you convert that Planned order to Production order , it will copy the Routing details based on the Order Type denpendt Parameters -OPL8-Routing -Alternative sequnce  and Automatic selection -3 option

         

        Thats why we have Capacity Requirement Planning  for Detail Capcity check and production order scheduling  .

         

         

        Note : Earlier to my first  reply , please note that you have option in CM21  enter sequence number  at order level which may applicable to you .CM21-Work Centre -exectute -Select the Order from order pool -Goto Order -Sequence number maintainence

         

        This number( sequence number operation /order )  that can be assigned to production orders or planned orders at the level of the task list header and is therefore valid for all the operations in an order.

         

        Hope this is clear .Revert if you nees farther help

        Regards

        JH

         

        Edited by: Jiaul Haque on Jul 5, 2010 3:32 PM

         

        Edited by: Jiaul Haque on Jul 5, 2010 4:01 PM

  • Re: planned order splitting during capacity planning
    Chanchai Chanwong
    Currently Being Moderated

    You can only change the alternative sequence in production orders.  Changing alt. seq. in planned order is not possible.