on 07-17-2010 1:14 PM
in report PTARQ-Time Accounts, the value displayed for "Entitlement Planned" is negative. But the quota has not been exceed, and the quota is set not to exceed in config. Why is it a negative value displayed?
below are the values displayed in PTARQ for one employee
entitlement=120 hrs
used=64hrs
unaproved=8hrs
approved=56hrs
Entitlement Used=56hrs
Entitlement Approved=0hrs
Entitlement Planned= 8- hrs (minus!) ???
Thanks,
Tiberiu
Edited by: Tiberiu Sasu on Jul 17, 2010 2:14 PM
Edited by: Tiberiu Sasu on Jul 17, 2010 2:15 PM
run the rptarqpost and the issue would be solved
During the intermiadiate run ie creation and approval, only simulation is done, no deduction rule ect is followed
it is done once leave is posted and it wil;l be rectified
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check if untransferred absences or being accounted here and also accrual entitlements that are not yet accumulated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.